3.2. Approval process
3.2.1. Threshold for approval requirement
For the purposes of section 48(b) of the Framework Regulations, the thresholds at which the prior written approval of the AFSA is required are when the relevant holding is increased:
- (a) from below 30% to 30% or more; or
- (b) from below 50% to 50% or more.
3.2.2. Approval process
(1) A Person who is required to obtain the prior written approval of the AFSA pursuant to section 48 of the Framework Regulations must make an application to the AFSA using the form prescribed in Schedule 3.
(2) Where the AFSA proposes to approve a proposed change of control, it will:
- (a) do so as soon as practicable and in any event within 30 days of the receipt of a duly completed application, unless a different period is considered appropriate by the AFSA and notified to the applicant in writing; and
- (b) issue to the applicant, and where appropriate to the Authorised Person, an approval notice as soon as practicable after making that decision.
(3) Where the AFSA proposes to object to or grant a conditional approval to a proposed change of control, it will follow the procedures in Schedule 1 to the Framework Regulations
3.2.3. Effect of AFSA approval or conditional approval
(1) An approval, including a conditional approval granted by the AFSA pursuant to GEN 3.2.1, is valid for a period of one year from the date of the approval, unless an extension is granted by the AFSA in writing.
(2) A Person who has been approved by the AFSA as a Controller of an Authorised Person subject to any conditions must comply with the relevant conditions of approval.